--- Our House: Timeline ---

Here's a reverse-chronological timeline of the progress:

Oct 00 Sold the house and moved out two weeks later
Aug 00 Put the house on the market
Mar 00 Planted palms and groundcovers next to main patio
Dec 99 Removed all remaining grass, and replaced with bark gardens
Sep 99 Formed path through native bush, and planted trees
Aug 99 Hung curtains in lounge, dining and bedrooms, at last!
Jul 99 Planted nine more privacy trees along the side boundary
May 99 Formed and planted side lawn
Apr 99 Covered most of back part with bark
Mar 99 The right-hand fence was built
Feb 99 The left-hand fence was built
Dec 98 Created the ponds and got first fish
Dec 98 Put up trellis for climbing roses
Nov 98 Formed and planted front lawn
Nov 98 Planted privacy trees
15 Oct 98 Earthmoving
12 Sep 98 Housewarming party!
Sep 98 Brick letterbox built
Sep 98 Imprinted concrete patio constructed
Aug 98 Imprinted concrete driveway constructed
15 Jul 98 Fridge integrated into kitchen
14 Jul 98 DishDrawer dishwasher installed
13 Jul 98 TV aerials installed
11 Jul 98 Moved in!!
9 Jul 98 Plumbing finished
Carpet laying
8 Jul 98 Kitchen finshed
Electrical finished
Tiling finished
7 Jul 98 Phone connected
Finishing touches
1 Jul 98 Under-tile heating in ensuite installed
29 Jun 98 Drainlaying
21 days notice to our landlord!
26 Jun 98 Tiling started
Gas appliances installed
24 Jun 98 Tiles delivered
22 Jun 98 Gas meter fitting and appliances delivered
Gas pipe in trench
19 Jun 98 Electrical fitting out started
Gas pipe in trench
18 Jun 98 Plumbing fitting out
17 Jun 98 Wallpaper hanging
Oven & DishDrawer delivered
14 Jun 98 Painting work completed
11 Jun 98 Met with two tilers
Cut shower bases
6 Jun 98 Painting work started
5 Jun 98 Kitchen installed
4 Jun 98 Bath and vanities installed
1 Jun 98 Gibbing work completed
27 May 98 Got more dirt from Neville's site
Correct spa bath arrived
22 May 98 Gibbing work started
21 May 98 Gib board (dry wall) arrived
Vanities arrived (along with wrong bath)
20 May 98 Plumber pre-piping work done
18 May 98 Wall insulation installed
Garage door installed
16 May 98 Most of the internal doors installed
Electrical pre-wiring completed
13 May 98 Garden window installed
11 May 98 Gas pre-piping done
8 May 98 Electrical pre-wiring started
Garden window arrived, again
5 May 98 Bricklaying started
Got heaps of dirt from Neville's site
1 May 98 Bricks arrived
30 Apr 98 Guttering added
28 Apr 98 Windows and other joinery installed
22 Apr 98 Roof tiles installed!
21 Apr 98 Roof tiles piled on roof
18 Apr 98 Soffits added
7 Apr 98 Fascia added
6 Apr 98 Roof tiles arrived on site
3 Apr 98 Finalised the kitchen design details
30 Mar 98 Signed up for gas connection and installation
24 Mar 98 Framing for the walls went up
19 Mar 98 Concrete floor poured
18 Mar 98 Hardfill for under concrete floor added
17 Mar 98 Footings blockwork completed
Framing arrived on site
9 Mar 98 Footings concrete poured
7 Mar 98 Footings reinforcements constructed
6 Mar 98 Footings trench dug
4 Mar 98 Finally, work has started; the site was profiled
21 Feb 98 Bought carpet; it was on special today
16 Feb 98 Told builder external house colours
Met with kitchen company
12 Feb 98 Met with gas and electrical companies
11 Feb 98 Topsoil scraped off site (piled at back)
5 Feb 98 Possession of the section
3 Feb 98 Signed Golden Homes contract
29 Jan 98 Council permits issued
29 Jan 98 Signed mortgage documents
21 Jan 98 Visited bank and opened account with them
20 Jan 98 Mortgage approved!
16 Jan 98 Got full house valuation report
14 Jan 98 Mortgage approved provisionally
9 Jan 98 Got brief house valuation report
7 Jan 98 Saw mortgage broker
19 Dec 97 Plans to Council for permits
11 Dec 97 Got house plans via fax
20 Nov 97 House plan drawing started
18 Sep 97 Home Show -- ideas for plans
13 Aug 97 Signed section contract
31 Jul 97 Found section